N. Wilson Street Project Update

Water main construction is anticipated to start the week of April 18th

 

Sewer lateral construction is anticipated to start the week of April 25th

 

Work is likely to begin near Fredonia Avenue and proceed north but that could change.

 

Parking on the street on N. Wilson will be prohibited once construction starts.

 

Garbage and recycling pickup will be as normal.